3232### 2. RC3_TASK_BREAKDOWN.md
3333** Purpose:** Detailed actionable task list
3434** Audience:** Developers, project managers
35- ** Length:** 490 lines
35+ ** Length:** 300 lines
3636
3737** What's Inside:**
3838- 86+ tasks with priorities (P0-P3)
@@ -50,7 +50,7 @@ This index provides quick navigation to all RC3 Phase 4 planning documents.
5050### 3. RC3_QUICK_REFERENCE.md
5151** Purpose:** Quick answers and status at-a-glance
5252** Audience:** Everyone
53- ** Length:** 419 lines
53+ ** Length:** 433 lines
5454
5555** What's Inside:**
5656- Executive summary
@@ -70,7 +70,7 @@ This index provides quick navigation to all RC3 Phase 4 planning documents.
7070### 4. RC3_IMPLEMENTATION_ROADMAP.md
7171** Purpose:** Week-by-week implementation plan
7272** Audience:** Project managers, team leads
73- ** Length:** 630 lines
73+ ** Length:** 711 lines
7474
7575** What's Inside:**
7676- 20-week detailed plan
@@ -133,8 +133,8 @@ RC3_PHASE4_EPIC.md (Overview)
133133## 📊 Quick Statistics
134134
135135** Total Planning Documentation:**
136- - 4 comprehensive documents
137- - 3,444 total lines
136+ - 5 comprehensive documents
137+ - 3,378 total lines
138138- 86+ tasks identified
139139- 64 critical (P0) tasks
140140- 18 high (P1) tasks
Original file line number Diff line number Diff line change @@ -35,7 +35,7 @@ Phase 4 is the final push to complete BitCell RC3 and achieve mainnet readiness.
3535
3636## 📅 Timeline
3737
38- ** Overall:** 32+ days (January 15 - February 15 , 2026 and beyond )
38+ ** Overall:** 16-20 weeks (January 15, 2026 - May/June 2026 )
3939** RC3 Target:** Q2 2026
4040
4141### Key Milestones